| saabski wrote: |
However, part of the time spent 'repairing' the outage was actually spent moving the snow to access the gate to the substation. It was still piled w/snow at 1:30 when I got off the shuttle there. Seems in future GMP would plow it out as soon as the snow stops to allow access?
Would have saved some time (how much I do not know) in the T/R -troubleshoot and repair-
|
I actually sent her a reply email to this effect, suggesting that they do like Waitsfield Telecom and pay LOCAL plow people well to make those substations a priority plowing for this very reason.
Edit 2:10pm: GMP lady called me to tell me that she agreed, the plowing was an issue, but fwiw, and frankly of little consolation, time was not lost since their electrician had not arrived on scene yet. They are building a detailed timeline to figure out what/when on details and then evaluate and modify noted deficiencies.